If you’re running a facility that relies on dry-type transformers, at some point you’ll need to stop one for maintenance, upgrades, or even emergency checks. I’ve been a transformer dry supplier for 12 years, and let me tell you—this isn’t something you can rush. Do it wrong, and you risk damaging the unit, or worse, putting your team at risk. I’ve seen a few over the years where someone skipped a step and ended up with a transformer that wouldn’t power back on, or had to replace parts that could’ve been avoided. So today, I’m breaking down how to stop a dry-type transformer safely, step by step, with the stuff I’ve learned from actual jobs. First, a quick note: this guide works for all types—whether it’s an Epoxy Resin Dry Type Transformer, an Indoor Dry Type Transformer tucked in a utility closet, or even an Outdoor Dry Type Transformer sitting outside in the elements. Oh, and if you’re at a substation, the Auxiliary Transformer in Substation has its own little quirks, which I’ll touch on too.

First things first—before you even touch the transformer, lock it out and tag it out (LOTO). This isn’t a suggestion, it’s non-negotiable. I’ve had a new tech try to skip LOTO once because they “knew the unit was off,” and someone across the site flipped the breaker by mistake. Scared me straight. Here’s how to do LOTO right: find the main disconnect breaker for the transformer (it’ll be in a panel nearby, usually labeled with the transformer’s ID). Turn it all the way off—don’t just switch it to “off” halfway, make sure it’s fully disengaged. Then, grab a lock (one per person working, if there’s more than one) and lock the breaker in the “off” position. Add a tag that says “DO NOT OPERATE—MAINTENANCE IN PROGRESS” with your name, your team’s name, and the date. For outdoor units, if it’s on a pad or a pole, make sure the disconnect is accessible and that no one can reach it from a ladder or something. For aux transformers at substations, sometimes they’re in a fenced area, so double-check that the fence is secured too. This step takes 5 minutes max, and it’s the most important part of the whole process. No exceptions.

Next, you need to discharge the residual charge. Even after you turn off the breaker, there’s a little leftover electricity in the transformer’s windings—this can shock you if you touch the wrong parts. I use a insulated discharge wand, the kind with a ground clamp that’s rated for the voltage of your transformer. Don’t use a regular screwdriver or a random wire—insulated tools only. For indoor epoxy-resin units, the windings are sealed, so you just need to find the terminal leads (they’re usually metal bolts on the top or side) and gently touch the discharge wand’s probe to each lead for 2-3 seconds. For outdoor units, since they’re exposed to weather a bit, wipe the terminals with a dry cloth first to get rid of dirt or moisture—water conducts electricity, so that’s a bad mix. If you’re working on an auxiliary transformer at a substation, the charge might be a bit higher because those feed other equipment, so hold the wand a little longer, like 5 seconds per lead. I always do a quick check after discharging too—use a multimeter set to AC volts, touch both leads, if it shows 0, you’re good. If it shows anything more than 5 volts, discharge again. That extra step saves you from a nasty jolt, trust me.

Now, depending on why you’re stopping the transformer, you might need to let it cool down first. If it was running right before you shut it off, the windings can get up to 100°C (212°F)—that’s hot enough to burn you, and if you start taking apart parts too soon, you could crack the epoxy resin on some units. For indoor transformers, which are usually in climate-controlled areas, let it cool for at least 2 hours if it’s been running for more than 8 hours. For outdoor units, especially in the summer, add another hour—metal cools slower when it’s hot out. Substation aux transformers often run continuously, so I tell my clients to plan for 3-4 hours of cool-down time. If you need to stop it quickly for an emergency, you can use a fan (insulated, obviously) aimed at the casing, but don’t blast cold air directly on the epoxy—sudden temperature changes can cause cracking, which defeats the whole point of a dry-type.

Once it’s cool and discharged, you can start accessing the main parts— but before you do that, prep your work area. If it’s an indoor transformer, clear the area around it of any tools, cables, or debris. You don’t want a wrench falling into the windings later. For outdoor units, make sure the ground around it is dry—if it rained that day, lay down some rubber mats to stand on, so you don’t slip and step in water. For substation aux transformers, the area is usually busy with other equipment, so mark your work zone with caution tape to keep other teams from walking in. Also, gather all the tools you need ahead of time—wrenches, screwdrivers, a soft brush for cleaning, and a level (if you’re checking alignment later). Don’t have to run back to the toolbox mid-job; that’s how you leave a wrench somewhere it doesn’t belong.

Now, removing the outer casing (the part that covers the windings) is next, and this part’s easy if you take it slow. For epoxy resin units, the casing is usually bolted on with 4-6 bolts around the edges. Loosen the bolts in a crisscross pattern (like how you change a tire) so the casing doesn’t warp—if you loosen all one side first, it can bend a little, which might make it hard to put back on. For outdoor casings, they’re a bit heavier, so have a partner help you lift it off—don’t try to do it alone; you can strain your back or drop it. For indoor units, the casing might have a few clips too, so check for those before pulling. Once the casing is off, don’t touch the windings with your bare hands—oil from your skin can cause hot spots when the transformer runs again. I use cotton gloves, no rubber ones (they can leave lint), and a soft brush to gently wipe dust off the windings. If there’s mold on the windings (common in damp indoor areas), use a dry microfiber cloth—don’t use water or cleaning chemicals, they can damage the epoxy coating.

Wait a second—what if you’re stopping the transformer for a part replacement, not just cleaning? Let’s say a fan on an outdoor unit died, or a terminal on an aux transformer is corroded. First, make sure you have the right replacement part. As a transformer dry supplier, I always tell clients to get the exact model number of their transformer—those number are on a plate on the side. Don’t guess, because a fan from a different model might not fit. When you’re swapping parts, make sure to disconnect any wiring carefully—label each wire with tape so you remember where it goes later. I once had a client mix up two wires on an aux transformer, and when they turned it back on, it shorted out and ruined the whole unit. Labeling takes 10 seconds per wire, saves thousands in repairs. For corrosion on terminals, use a wire brush rated for electrical parts, sand the corrosion off gently, then apply a thin layer of dielectric grease to prevent it from coming back.

Auxiliary Transformer in Substation suppliersIndoor Dry Type Transformer

Now, if you’re doing more heavy-duty stuff, like checking the core (the big metal part in the middle), here’s a tip: don’t touch the core with metal tools if it’s charged. Wait, no—you already discharged it, right? But double-check. The core is heavy, so when you lift it out, have at least two people. For epoxy resin units, the core is sealed, so you just need to inspect it for rust or loose bolts. For outdoor units, the core might have a little rust from rain, so a light sanding and a coat of rust-resistant paint (rated for electrical equipment) works. For substation aux transformers, the core is under more load, so make sure all the connections are tight—loose bolts can cause vibration, which wears out parts faster.

Once you’re done with whatever you needed to do, putting the transformer back together is just as important as taking it apart. First, check that all tools are accounted for—no wrenches, screws, or rags left inside the casing. I always do a quick count: I brought 5 wrenches, I leave with 5. For indoor units, make sure the area around it is clean, no dust or debris. For the casing, put it back on the same way you took it off—align the holes, then tighten the bolts in the same crisscross pattern, to the torque specified in the transformer’s manual. If you don’t have the manual, as a supplier, I can send you one, or look up the torque online with the model number. Don’t over-tighten the bolts—you can crack the casing or damage the windings. For aux transformers at substations, double-check that the wiring is all connected, no loose ends, and the insulation is intact.

Now, the final step before turning it back on: remove the LOTO tags and locks. Only the people who put them on can remove them—no one else. If someone else put the LOTO on, ask them to take it off. For outdoor units, make sure the disconnect is clear, no ladders or tools nearby. For indoor units, close the panel door, make sure it’s latched. For substation aux transformers, alert the substation operator that you’re done and the transformer is ready to power on. Then, slowly flip the breaker back on—don’t just throw it all the way. Let it sit for a minute, listen for any weird noises (buzzing is normal, grinding or hissing is not). Check that the fans are running if it’s an air-cooled unit, and the temperature is within the normal range (usually between 30-60°C, depending on the model). If all that checks out, you’re good.

Wait, a few common mistakes I see people make: first, skipping the LOTO step. I can’t tell you how many times I’ve had a client call me panicking because someone flipped the breaker while they were working. Second, not discharging the charge—even a small jolt can send you falling off a ladder, which is more dangerous than the shock itself. Third, rushing the cool-down time. I had one client who stopped a transformer right after it shut off, took apart the casing, and the windings were so hot they melted a little of the epoxy. Cost them $15k to replace, when the cool-down time was only 2 more hours. Fourth, not labeling wires when swapping parts. As I said earlier, that leads to short circuits.

If you’re not sure about any step—whether it’s checking the residual charge, tightening bolts, or swapping parts—don’t hesitate to reach out. I’m a transformer dry supplier, and my team and I have walked through hundreds of these jobs. Whether you need help with an Epoxy Resin Dry Type Transformer, an Indoor Dry Type Transformer, or an Auxiliary Transformer in Substation, we can walk you through the process, or even send a tech to help if it’s a big job. To talk through your specific needs, just reach out to our team—we’re here to make sure your transformer is stopped safely, every time.

References:

  1. National Fire Protection Association (NFPA 70E): Standard for Electrical Safety in the Workplace
  2. Institute of Electrical and Electronics Engineers (IEEE C57.12): Standard for Liquid-Immersed and Dry-Type Power Transformers, Voltage 601 V Through 115 kV
  3. Occupational Safety and Health Administration (OSHA): Lockout/Tagout Procedures for Electrical Equipment